*
White motor yachts beside a clean concrete marina edge, with teal water, palms and low coastal architecture in warm winter sunlight.

What's Going Up Around Lighthouse Point This Winter, From the Yacht Club to Sample Road

November 12, 2026

Barricades now line the north side of Northeast 39th Street between Northeast 23rd and 24th Avenues. They keep pedestrians off the seawall and keep cars from parking along the right-of-way beside it. The city's November 2026 bulletin says the area will stay blocked "for an extended period." Northeast 39th Street is also where the planned sidewalk on Northeast 27 Terrace starts. That sidewalk runs north to the entrance of the Lighthouse Point Yacht Club, where the old clubhouse came down in September.

This winter's three biggest construction stories in Lighthouse Point are a city emergency, a sidewalk paid for by a private developer, and a private club's rebuild. All three meet on the same short stretch of town. Sample Road and the citywide tree trimming come later and reach further, but the work that changes how you get around between now and spring starts on Northeast 39th Street.

The seawall on Northeast 39th Street jumped the line

The city maintains 15 seawalls. In October, the commission gave Kimley-Horn & Associates an emergency design contract for $143,700 to repair several of them. City staff found the damage on Northeast 39th Street in October. The New Pelican reported that City Administrator Ross Licata called the roughly 70-year-old wall "damaged beyond repair." It is on a work list to be expedited, and the rebuild needs custom-designed concrete pilings and seawall panels.

Northeast 39th Street is only one stop on the repair list. The same New Pelican report names these walls:

  • East of Lighthouse Drive at Northeast 48 Court and Northeast 48 Street
  • Northeast 39th Street, north side, between Northeast 23rd and 24th Avenues
  • Lighthouse Drive at Northeast 34 Terrace
  • The end of Northeast 36th Street

Work is expected to begin in late December. Mayor Kyle Van Buskirk told the paper the seawalls "require major repairs" and that the project needs "significant supervision to complete within an accelerated timeline." That schedule is why Licata, who announced his retirement in August after three years as city administrator and 20 as police chief, will stay at City Hall at least through January. Until the new wall goes in, the barricades on Northeast 39th Street are the part of this project you will see most.

Northeast 27 Terrace gets a sidewalk the club's developer pays for

Head east along Northeast 39th Street and you reach Northeast 27 Terrace, one of the two roads into the Yacht Club. In August, the commission approved a 1,300-foot sidewalk on the east side of the Terrace, from Northeast 39th Street to the club entrance.

The money comes from an unusual place. Under a 2022 agreement tied to the club's redevelopment, the city builds the sidewalk and developer Terry Paterson pays for it. City Engineer Ted Green put the estimate at $329,000. That is more than twice the $143,700 the city is spending to design its seawall repairs, and none of it comes out of the city's budget.

The New Pelican reported that the city surveyed residents of the Terrace in July. Most favored the sidewalk, citing heavy traffic and a very dark street. At the August meeting, one resident proposed making Northeast 27 Terrace and the club's other entrance on Northeast 30th Street a one-way pair, one for entering and one for leaving. According to the paper, he was told the already-approved site plan does not allow that. Green is in charge of building the sidewalk.

What's rising at 2701 NE 42nd Street

At the end of the Terrace is the project behind the sidewalk. Florida YIMBY reported in October that construction has started on a redevelopment of roughly $250 million at the Lighthouse Point Yacht Club. Paterson's firm, Paterson Project Management Inc., is developing and building it, and Annie Carruthers of Insite Design Group is the architect.

The private club opened in 1961. When the clubhouse came down in September, The New Pelican wrote that it had hosted the city's charity events, mariners and tennis players for six decades. The new clubhouse will cover 45,850 gross square feet, including about 35,500 square feet of air-conditioned space and a 19,475-square-foot rooftop. The plans include:

  • An indoor fine dining restaurant, piano lounge and outdoor tapas bar
  • A second-floor banquet hall for up to 280 people that can be divided into two rooms
  • Five lighted Har-Tru tennis courts, two at ground level and three on the roof
  • A 10,400-square-foot fitness, locker room and spa complex
  • A 2,500-square-foot children's center with an indoor basketball court
  • A Junior Olympic-sized pool

The 78-slip marina near Hillsboro Inlet stays. The site will also hold 21 three-story townhomes in six buildings plus one future single-family waterfront home, and townhome ownership includes club membership. Those homes are why the Terrace's traffic came up at City Hall at all.

Work is being done in phases so the club can keep running. According to Florida YIMBY, members keep the existing pool, restaurant and bar, fitness center, tennis and marina during construction. The club's development page estimates about 28 months of work and a grand opening in the third quarter of 2028. Five townhomes and the single-family home are scheduled to start after the clubhouse phase.

The groundbreaking came after a long wait. The first land-use application was filed in 2018, followed by about five years of entitlement proceedings and 28 public hearings. A redesign to handle a higher occupant load under updated life-safety rules added about 18 months. Permits were finished in 2024, but tighter construction lending pushed back the start. In early 2026, Paterson bought out his foreign investment partners. "For people driving by a construction site, it can look like a project simply starts one day," Paterson told Florida YIMBY.

Who's building what, and who's paying

Project Where Paid by Timing
Seawall repairs NE 39th St; NE 48 Ct and NE 48 St; Lighthouse Dr at NE 34 Terrace; end of NE 36th St City, with a $143,700 emergency design contract Expected to start late December
NE 27 Terrace sidewalk East side, NE 39th St to the Yacht Club entrance Developer Terry Paterson, about $329,000 estimated Approved August 2026
Yacht Club redevelopment 2701 NE 42nd St Paterson and investing club members Grand opening expected Q3 2028
Sample Road improvements Federal Highway to the Intracoastal County surtax, about $1.9 million Construction expected Q1 2027
Right-of-way tree trimming Federal Hwy, Lighthouse Dr, Sample Rd, NE 49th St City, up to $200,000 Underway

The two biggest dollar figures, the club and Sample Road, are both mostly future work. The project you'll notice first is the cheapest one, a design contract for a wall that has already been fenced off.

After the holidays, the work moves to Sample Road

Sample Road is the city's next big job. The city has received county surtax funding for the construction phase of the Sample Road Improvement Project, which covers the stretch from Federal Highway east to the Intracoastal Waterway. The plan includes:

  1. Shared-lane markings for cars and bicycles
  2. Sidewalk and ADA improvements
  3. Fixes for the existing pedestrian crosswalks
  4. Minor drainage changes
  5. Milling, resurfacing and new striping
  6. Median cuts and intersection crossings

The New Pelican reported that the commission awarded the project to Kimley-Horn in October at an estimated $1.9 million. The city's bulletin says construction will begin in the first quarter of 2027. Kimley-Horn is the same firm designing the seawall repairs, so one engineering firm is handling both of the city's largest public works projects this season.

You may meet the tree crews first. In August, the commission approved up to $200,000 to trim trees planted in rights-of-way years ago that are now causing problems. The crews started at the north city limits, and the route includes Lighthouse Drive, Sample Road, Federal Highway and Northeast 49th Street. The November bulletin says the work was moving onto Federal Highway and asks drivers to watch for flaggers and follow posted signs.

Wondering how the Yacht Club rebuild, the new Northeast 27 Terrace sidewalk or the coming Sample Road work affects your own street or a home you're thinking about? Matthew Heinz follows these Lighthouse Point projects closely and is happy to talk it through with you. Schedule a Free Consultation.

Work With Matthew

Get assistance in determining current property value, crafting a competitive offer, writing and negotiating a contract, and much more. Contact him today.